ABS & Co secures High Court victory for M/s Zahir Khan & Brothers in Retention Money Dispute against RDA

ABS & Co has successfully represented M/s Zahir Khan & Brothers (ZKB) before the Lahore High Court (Rawalpindi Bench) in a landmark constitutional and infrastructure dispute against the Rawalpindi Development Authority (RDA) (Writ Petition No. 1817 of 2025). In a judgment authored by Mr. Justice Mirza Viqas Rauf on October 20, 2026, the Court set aside the RDA’s impugned directive of May 7, 2025, which had placed ZKB’s retention money in abeyance on account of unresolved audit paragraphs.

The dispute arose out of two major contracts awarded to ZKB, a leading Pakistan Engineering Council (PEC) No-Limit construction company, following competitive bidding for the Rawalpindi–Islamabad Metro Bus Project in 2014: Package-I Works (Flashman Hotel to Committee Chowk), valued at PKR 4.701 billion, and Package-IV Works (Centaurus Mall to Shaheed-e-Millat Road), valued at PKR 2.868 billion. Both agreements were governed by the FIDIC Conditions of Contract (Red Book, 1987, reprinted 1992). Substantial Completion Certificates were duly issued in May 2015, and the respective Defects Liability Periods (DLP) expired in May 2017, after which the first half of the retention money and performance guarantees were released. However, RDA withheld the second half of the retention money, citing pending audit objections before the Public Accounts Committee (PAC) and arguing that a formal Defects Liability Certificate (DLC) had not been issued.

Unlike earlier judicial precedents involving retention money disputes—where formal Defects Liability Certificates had already been issued prior to litigation—this case presented a critical contractual hurdle because the Engineer had not issued a DLC. RDA attempted to distinguish settled case law on this precise ground, contending that the absence of a DLC precluded ZKB from claiming the remaining retention money.

Representing ZKB, ABS & Co successfully demonstrated to the Court that under a joint reading of Sub-Clauses 60.3 and 62.1 of the FIDIC Red Book 1987, the issuance of a DLC is not required for the release of the second half of the retention money; rather, only the expiration of the Defects Liability Period is necessary. Persuaded by these submissions, the Court underscored that the proviso to Sub-Clause 62.1 expressly clarifies that the issuance of a DLC shall not be a condition precedent to the payment of the second moiety of retention money. Furthermore, since the Engineer was contractually obligated to issue the DLC within 28 days of the DLP’s expiration, the Court held that RDA could not take advantage of its own Engineer’s lapse to withhold ZKB’s dues. Reaffirming that audit paragraphs are merely recommendatory probes that cannot justify suspending admitted contractual payments without due process, the Court quashed RDA’s impugned letter.

The ABS & Co team advising on this matter included Ahmer Bilal Soofi, Bakhtawar Bilal Soofi, Usman Jillani and Anza Mahmood Lilla.